Project Schedule

(Updated April 2022)

CONSTRUCTION SCHEDULE

General construction can occur during the hours of 7:00 a.m. to 8:00 p.m., seven days a week, including holidays.
Pile driving will occur on weekdays between approximately 8 a.m. and 5 p.m., excluding holidays.

Scheduling exceptions may be considered in case of major weather events or other extraordinary circumstances that prevent pile driving from proceeding.

*All dates/time periods and construction activities are subject to change

 

April 2022

Third Street, Channel Street, and Mission Rock Street

Underground Utilities
  • Gas line installation

Block A

Vertical construction continues
  • Continue interior build-out

 

Block B

Vertical construction continues
  • Concrete pours

Block F

Pile-supported foundations
  • Driving piles M-F 8 a.m.- 5 p.m. 

Block G

Buildout of terraces

Start of interior painting

Site-wide

Excavation and off-haul
  • Excavation and off-haul work occurs periodically over the duration of the construction period and at various locations of the construction site
  • The three entry and exit points are at Terry Francois Boulevard and at Third Street

Installation of utility crossings

  • Includes District Energy System (DES), sanitary sewer, storm drain

Lightweight cellular concrete pours

  • Occurs on-site

China Basin Park

  • Excavation, off-haul, and underground utilities

May - June 2022

Block A

Vertical construction continues

Block B

Building foundation substantially completed

Precast installation to begin

Block F

Pile-supported foundations
  • Driving piles M-F 8 a.m.- 5 p.m. 

Block G

Completion of precast installation

Site-wide

Street improvement work
  • Asphalt concrete paving
  • Landscaping

China Basin Park

  • Excavation, off-haul, and underground utilities

July - September 2022

Block A

Vertical construction continues

 

Block B

Vertical construction continues

Block F

Vertical construction continues

Block G

Substantial completion

Site-wide

Street improvement work

China Basin Park

Work continues

October - December 2022

Block A

Vertical construction continues

Block B

Vertical construction continues

Block F

Vertical construction continues

Block G

Final improvements

Site-wide

Street improvement work

China Basin Park

Work continues