Project Schedule

(Updated 7/6/21)

CONSTRUCTION SCHEDULE

General construction can occur during the hours of 7:00 a.m. to 8:00 p.m., seven days a week, including holidays.
Pile driving will occur on weekdays between approximately 8 a.m. and 5 p.m., excluding holidays.

Scheduling exceptions may be considered in case of major weather events or other extraordinary circumstances that prevent pile driving from proceeding. Different scopes of work require different work hours which are indicated respective to scope of work below.

The schedule below covers the current schedule for the rest of 2021. Scroll further down to view October through December.

*All dates/time periods and construction activities are subject to change

 

Mission Rock Phase 1

July 2021

Third Street

Underground Utilities – (to resume in mid-July)
  • Sanitary sewer work
    • M-F 7:00 a.m. – 3:00 p.m. 
    • Between Channel St. and the Third Street Bridge. 
    • Street lanes shift as work progresses (See June Community Update for more info)

Block G

Structural steel erection – LVL-3 to be completed in early July

Foundation slab work and waterproofing

Soil backfill

Personnel hoist erection

Block A

Shoring and excavating

Install below grade waterproofing

Tower crane erection

Block B

Pile-supported foundations 
  • Driving piles M-F 8 a.m. – 5 p.m.

Site-wide

Excavation and off-haul
  • Excavation of on-site roadways 
  • Excavation and off-haul work occurs periodically over the duration of the construction period and at various locations of the construction site
  • The three entry and exit points are at Terry Francois Boulevard and at Third Street

Installation of deep utility crossings

  • Includes District Energy System (DES), sanitary sewer, storm drain

Lightweight cellular concrete (LCC) pours

  • Occurs on-site

August-September 2021

Third Street

Underground Utilities
  • AWSS tie-ins
  • Storm drain catch basins
  • Dry utility crossings
  • Gas line installation

Block G

Underground waterproofing to be completed

Concrete foundation work to be completed

Steel erection to be completed towards end of Q3

Block A

Start of concrete foundations

 

Block B

Pile-supported foundations 
  • Driving piles M-F 8 a.m. – 5 p.m.
  • Estimated to conclude by the end of August

Site-wide

Excavation and off-haul
  • Excavation and off-haul work occurs periodically over the duration of the construction period and at various locations of the construction site
  • The three entry and exit points are at Terry Francois Boulevard and at Third Street

Installation of utility crossings

  • Includes District Energy System (DES), sanitary sewer, storm drain

Lightweight cellular concrete pours

  • Occurs on-site

October-December 2021

Third Street

Underground Utilities

Block G

Building structure

Building skin

Interiors

Block A

Steel erection

Personnel hoist erection

Block B

Shoring and foundations

Start of steel erection

Building structure

Block F

Pile-supported foundations
  • Estimated to start in fall or winter
  • Driving piles M-F 8 a.m.- 5 p.m. 

Site-wide

Excavation and off-haul
  • Excavation and off-haul work occurs periodically over the duration of the construction period and at various locations of the construction site
  • The three entry and exit points are at Terry Francois Boulevard and at Third Street

Installation of utility crossings

  • Includes District Energy System (DES), sanitary sewer, storm drain

Lightweight cellular concrete pours

  • Occurs on-site