Project Schedule

(Updated March 2023)

CONSTRUCTION SCHEDULE

General construction can occur during the hours of 7:00 a.m. to 8:00 p.m., seven days a week, including holidays.

Scheduling exceptions may be considered in case of major weather events or other extraordinary circumstances that prevent construction work from proceeding.

*All dates/time periods and construction activities are subject to change

 

March 2023

Block A

Exterior
  • Terrace buildouts
  • Landscaping
  • Exterior finishes

Interior

  • Unit buildouts
  • Interior finishes

Block B

Exterior
  • Terrace buildouts and landscaping

Interior

  • Lobby finishes
  • Commissioning of the Black Water Treatment System

Block F

Vertical construction continues

Weeknight night work beginning March 8: Façade installation

Block G

Substantial completion of building
  • Storefront buildouts
  • Interior finishes

Tenant improvements ongoing

Site-wide

Streetscapes

China Basin Park

  • Lightweight Cellular Concrete (LCC) pours
  • Excavation
  • Geofoam installation
  • Tree installations

April - June 2023

Block A

Interior and exterior finishes

Block B

Interior and exterior work continues

Block F

Vertical construction continues

Weeknight night work: façade installation

Block G

Tenant improvements ongoing

Site-wide

Street improvement work

China Basin Park

West side
  • Decorative hardscape
  • Utilities’ installations

East side

  • Excavation
  • Geofoam installation
  • Lightweight Cellular Concrete (LCC) pours