Project Schedule

(Updated October 2023)

CONSTRUCTION SCHEDULE

General construction can occur during the hours of 7:00 a.m. to 8:00 p.m., seven days a week, including holidays.

Scheduling exceptions may be considered in case of major weather events or other extraordinary circumstances that prevent construction work from proceeding.

*All dates/time periods and construction activities are subject to change

 

October - December 2023

Block A

Building finishes continue

Block B

Building finishes continue

Block F

Exterior
  • Completing balconies, planters, handrails and most of the façade

Interior

  • Completing rocking, taping, primer and first coat of paint
  • Door, frames and bathroom tiles
  • Kitchen casework
  • Wood flooring

Block G

  • Building finishes continue
  • Tenant improvements ongoing

Site-wide

Streetscape work continues

China Basin Park

  • Utility work
  • Restroom installations
  • Landscaping
  • Decorative concrete
  • Bay Trail

Third Street

Read more HERE

Q1 2024

Block F

Interior and exterior work continues

Site-wide

Street improvement work

China Basin Park

The inland portion of the park is projected to be completed in Q1 2024

Q2 2024

Block F

Parcel F is projected to be completed in summer 2024